Supertech Builders vs RERA Appellate Tribunal
Citation: Civil Appeal No. 1120 of 2022
Judicial Precedent & Core Ruling
Under RERA 2016, developers are strictly liable to refund the amount with interest or hand over possession, and cannot bypass the statutory timeline using generic force majeure clauses.
Homebuyers in Noida complained of delayed flat possession; the builder claimed pandemic-related force majeure as a defense.