Court 1

Supertech Builders vs RERA Appellate Tribunal

Date: Nov 04, 2022
Homebuyers filed complaints regarding delayed possession of flats in Noida. The builder argued force majeure due to the pandemic. The Court held that under the Real Estate (Regulation and Development) Act (RERA) 2016, developers are strictly liable to refund the amount with interest or hand over possession. The strict timeline under RERA cannot be bypassed using generic force majeure clauses in builder-buyer agreements.